General sequence of Water Main Pipe laying works.
- Site survey and setting out.
- Site clearing.
- Earthwork and trenching
- Pipe laying and Jointing works
- Piling to Man hole/ service hall/valve chamber
- Piling to anchor Block/thrust block
- Construction of man hole /chamber/bridge/Thrust block
- Testing
- Rectification of pipe ( if any)
- Testing and commissioning
- Back filling to Pipe trench
- Site tidying prior to handing over for completion
- Handing over for completion.
*Item no.8 can be perform segment by segment
( lat say every 100m of installed and jointed pipe.)
Type of testing to be performed.
- Pressure test.
- Leakage test
- Welding test ( in the case of mild steel pipe is in use)