REQUEST FOR INSPECTION
|
||||||||
CONTRACT NO:
PROJECT TITLE:
|
||||||||
REFERENCE NO:
|
DATE:
|
|||||||
TO:
|
ATTENTION:
|
|||||||
ACKNOWLEDGE RECEIPT BY:
DATE:
|
||||||||
We hereby request for inspection on :
For the following work:(Tick in the
box below (√))
|
||||||||
BUILDING WORK
|
||||||||
Boundary setting out
|
Building setting out
|
Setting out ( specify):
|
||||||
earthwork
|
Foundation
|
Beam
|
Column
|
|||||
Staircase
|
Reinforcement
|
Formwork
|
Roof truss
|
|||||
Slab
|
Perimeter drain
|
Apron slab
|
Wall/partition
|
|||||
Roof covering
|
Door frame
|
Door leave
|
Window frame
|
|||||
Window leave
|
Rain water drain Pipe
|
Gutter
|
Plastering
|
|||||
Painting
|
Floor Screeding
|
Floor tile
|
Wall tile
|
|||||
Water Proofing
|
Septic tank
|
Other :
|
||||||
CIVIL WORK
|
||||||||
Earthwork
|
Road subgrade
|
Road sub base
|
Road base
|
|||||
Sewage manhole
|
Waste water manhole
|
Drain Alignment
|
Road Alignment
|
|||||
Road side drain
|
Flexible Pavement
|
Fencing
|
culvert
|
|||||
Road kerb
|
Road Marking
|
Signages
|
||||||
Mechanical & Electrical works
|
||||||||
Internal water pipe
|
External Water pipe
|
Water tank
|
switches
|
|||||
conduit
|
wiring
|
Power point
|
Lighting
|
|||||
Lightning arrester
|
MCB
|
DB
|
MSB
|
|||||
Cold water fitting & accessories
|
Electrical fitting & Accessories
|
|||||||
Other:
|
||||||||
Location:
|
||||||||
SO/SOR/RE/COW
The above work inspected on :
Inspected by:
|
Witness By Contractor:
Signature:
Date:
|
|||||||
Approved (
) Not Approved ( )
Remarks:
|
Related Topic:
RFI
Request For Information 2010
Request for information form 2012
Inspection form for reinforcement installation
Document control and Correspondance Document Register
Buy your most needed form at Amazon. Click below and buy