Step by step general guideline).
- Received construction Drawings
- Engage a License Surveyor
- Site boundary / Right of way setting out
- Surveyor to take all the existing ground level within the R.O.W for control and calculation purpose.
- Submit for approval all the survey works done on site prior to Site clearing works
- Start site clearing
- Setting out for road center line, road edge, road side drain and all necessary level
- Submit for approval all the survey works done at site prior to any earthwork
- Upon Approval, Proceed with the earthwork (Construction of the Subgrade) to achieve the design level.
- Construction of the road must be done as the approved project quality plan and method statement.
- Perform the Quality check according to the Project Quality Plan (PQP) and method statements to confirm to the design requirements.
- Upon achieving the design requirements for the subgrade, set up the second stage level control for the sub-base work and submit for approval prior to sub-base work.
- Upon approval proceed with the sub-base work.
- Perform QAQC Check as per approved PQP.
- Upon achieving the design level, submit for inspection and approval to proceed with the road-base work.
- Set up the control level for the road-base work.
- Submit for approval.
- Upon approved, proceed with the road base work.
- Repeat QAQC Procedure as required in Approved PQP for road-base work.
- Upon achieving the design level for the road-base, submit for inspection.
- Only proceed with the pavement work when the constructed Road-base is approved and accepted by client or their superintending officer. ( If any)
- Installation of the road furniture.
- Handing over for completion.
- Bingo…..The PHYSICAL WORK IS COMPLETED.