Wednesday, October 12, 2011

How to Construct A Proper Road


Step by step general guideline).
  1. Received construction Drawings
  2. Engage a License Surveyor
  3. Site boundary / Right of way setting out
  4. Surveyor to take all the existing ground level within the R.O.W for control and calculation purpose.
  5. Submit for approval all the survey works done on site prior to Site clearing works
  6. Start site clearing
  7. Setting out for road center line, road edge, road side drain and all necessary level
  8. Submit for approval all the survey works done at site prior to any earthwork
  9. Upon Approval, Proceed with the earthwork (Construction of the Subgrade) to achieve the design level.
  10. Construction of the road must be done as the approved project quality plan and method statement.
  11. Perform the Quality check according to the Project Quality Plan (PQP) and method statements to confirm to the design requirements.
  12. Upon achieving the design requirements for the subgrade, set up the second stage level control for the sub-base work and submit for approval prior to sub-base work.
  13. Upon approval proceed with the sub-base work.
  14. Perform QAQC Check as per approved PQP.
  15. Upon achieving the design level, submit for inspection and approval to proceed with the road-base work.
  16. Set up the control level for the road-base work.
  17. Submit for approval.
  18. Upon approved, proceed with the road base work.
  19. Repeat QAQC Procedure as required in Approved PQP for road-base work.
  20. Upon achieving the design level for the road-base, submit for inspection.
  21. Only proceed with the pavement work when the constructed Road-base is approved and accepted by client or their superintending officer. ( If any)
  22. Installation of the road furniture.
  23. Handing over for completion.



  24. Bingo…..The PHYSICAL WORK IS COMPLETED.

No comments:

Post a Comment