METHOD STATEMENT FOR TIMBER (BAKAU) PILING WORKS: DRAINAGE AND PERIMETER FENCING.
** this is only applicable for the requirement of one length (3.6m length) Timber (bakau) Pile by the method of excavator push-in.
- Setting out of piling point as shown in the construction drawing.
- Submission of the request for inspection for the approval and proceeding with the following works to the Superintending Officer (S.O) or Superintending Officer Representative (S.O.R).
- Pile driving works shall only proceed after receiving acceptance and approval from S.O or S.O.R's.
- Prior to proceed with the pile driving works the dimension of the timber (Bakau) pile shall first be inspected by S.O. or S.O.R's to confirm to specification and the construction drawing requirements. There shall be no timber (Bakau) pile allow for the works if it is does not fulfill the specifications and requirements of any as stated in the contract or construction drawings.
- Driving of timber (bakau) pile shall be as follows;
a). Positioning of the timber (Bakau) pile shall be as per approved pile point as agreed in the setting out. The eccentricity of the pile shall be as accurate as possible or as advice by the S.O or S.O.R's.b). At any point of the pile, its verticality shall be continuously monitored to ensure that the vertical alignment of the pile as straight as possible or as advise by the S.O or S.O.R's.c.) The pile push-in by the method of excavator push-in than shall proceed until the whole one length penetrates into the ground or until the pile set.d.) Record of the pile driving works shall be recorded properly using the pile driving work record form.
**Note: No test pile or static load test is required for this one length timber (Bakau) pile is needed unless requested by the S.O or S.O.R's.
why timber bakau pile only have one length?
ReplyDeleteIt is not necessary that the Bakau pile always one length. It is all depend on the design it self. If the During the design stage and by calculation prove that one length of bakau pile is sufficient to cater for the loading, then the designer will specified that only One length of bakau pile is needed. However there always note being inserted for the piling item. The notes always mention that the quantity for piling is provisional. Bakau pile usually applied to the foundation for perimeter drain, fencing or small drain. Sometimes it also being used as foundation forseptic tank or sewerage treatment plan with a small capacity. As for the above method statement it is derive from a project which specified only one length of the bakau pile is needed. If it is more than one length, then the method for jointing shall be included and also the pile driving method might be different if it shall be "pile to set" which is end bearing pile.
Deleteanybody has Risk Assessment and Safe Work Procedures for Installation of Bakau Piles using an excavator to punch in.??
ReplyDeletePlease share with me liow@hotmail.sg
Thanks For sharing the useful information about Piling Repair
ReplyDelete