Sunday, November 4, 2012

Free inclement weather record

Incremental weather is an enemy to contractor, consultant and client when it come to construction issue.

Weather is an important factor and record that need to be track from time to time. in the even that the weather at the construction site had become unusual compare to the previous year, this type of record will be essential and become the most important document in obtaining the extension of time for contractor application to client.

Apart from this record, the rainfall data MUST also be recorded to proved that the rainfall for the particular day in beyond the expectation and had affected the progress of the construction activity. Rainfall data can always be captured by placing rainfall gauge at site. Below are link to the sample of Daily Record.

Daily Weather Record

In Sarawak the normal practice in the event there is no rainfall data gauge been provided at site, client, contractor and consultant will always resort to the nearest rainfall station which own by Hydrological Department that will provide the rainfall data for them to do assessment on the exceptional incremental weather for the purpose of extension of time. 

Wednesday, October 17, 2012

Quality Documentation filing


Construction works is not only about constructing structure, infrastructure, etc. that we need to focus on. In order to have a smooth flow of construction work, there is another area that most of contractor always overlook. The area that I mentioned here is no other than clerical works.

Normally most of us just leave the filing process to our general clerk. It is OK if the appointed clerk know how and have some knowledge of ISO system but if they are only average general clerk, we might facing difficulty in finding the records of  construction. Therefore a proper filing system shall be create and follow to ensure easy track back on all the issue pertaining to our construction.

In general project correspondence is divided into two (2) Major component that is Incoming correspondence and Out-going Correspondence  From this two major category, we than can break it out to another 3 sub major category that is Client, Consultant, Local Authorities/Local Council and miscellaneous. This category than can be further divided into different type of category such as monthly progress report, QAQC Report, Meeting, Progress payment or claim and etc..

Below is How I do my breakdown for the purpose of my project filing.

GUIDE FOR PROJECT FILING

The link below is for a more proper filing system.
QUALITY FILING SYSTEM