Managing the construction site.
Good practice of the construction management of the construction site is always the key to a successful construction project. To have a proper construction management of the site, it always falls back to the basic, that is the CHECKLIST. Among the item that need continuous monitoring and tracking are as bellow.
- Machineries
- Plant
- Equipment
- Labour or manpower
- Health and safety aspect such as Personal protective Equipment (PPE)
- Procurement of the material, machinery, man power, plant
- Quality assurance & Quality control checklist for every aspect of work.
- Method statement Checklist
- Approval of material Checklist.
Some of the common checklist form is as follows.
Contract No :
CONS2U/BLOG/2010
Project Title : Construction of 3 unit of 4 storey Residential Apartment.
Checklist of Machinery/Plant/Equipment/Manpower.
item | Type of machinery | Locations where machine will be deploy. | Machine capacity | QTY | Date Start | Duration | |||
1 | excavator | External drainage | 0.5 cu.m | 1 | 21.04.2006 | 14 days | |||
2 | Dump truck | External drainage | 3 tons | 1 | 21.04.2006 | 14 days | |||